I am making these updates far from when I actually did the work so they will probably be briefer than usual as I doubt I can remember what I did! For a total change of pace I thought I would…
Category: Fuselage
Attaching the Horizontal Stabiliser (2h)
Here’s one of those thirty minute jobs that took two hours. The stabiliser was already clamped in place for drilling but I realised I wouldn’t be able to do anything while the attach brackets were clecoed on the top skin.…
Season 5 Begins – Seats and Tail (1hr 30m)
Seems like it has been forever but I am finally back in the hangar, drilling holes and riveting metal. A bit of a late start to the season thanks to a great trip to Australia but here we go with…
Seats (1h 30m)
I had wanted to get back to the tail this weekend but the replacement gussets from Zenith had not arrived so I switched my attention to the seats. Although the seats won’t go in until quite near the end it…
Working at the back (2.5 hr)
The last post ended on a downer but the good news is that I think there is no need to worry as where the two parts of the tail meet there are some washers that should sort the spacing out.…